Bishkek, Nov. 20, 2026. /Kabar/. Approximately 800 meters of the 1.5-kilometer-long diversion tunnel for the 30 MW Papan Hydropower Plant (HPP), currently under construction in the Kara-Suu district, have been excavated.
According to the ministry of energy, the construction work is being carried out by "Chakan HPP" OJSC in collaboration with the "Kyrgyz-Chinese Joint Hydropower Construction Company" LLC, within the framework of a public-private partnership.
Currently, excavation work for the power plant building and the construction of the shaft for the water intake gate are underway. Additionally, the installation of supports for a 110 kV power transmission line has been completed, and a temporary 10 kV power supply system for the water intake facility has been connected to the grid.
Once commissioned, the hydropower plant being built at the Papan Reservoir will generate additional electricity annually, contributing to an increase in the country's power generation capacity.