Bishkek, March 10, 2026. /Kabar/. Chakan HPP continues to implement the Papan HPP construction project, Ministry of Energy reports.
According to the information, a temporary road with a total length of 9.2 kilometers leading to the station building is currently being built, and the construction of a town for specialists is almost completed.
In addition, a project for a 110 kV power line has been prepared, and the necessary permits for tunnel construction and blasting are being drawn up.
In addition, a preliminary environmental impact assessment was developed to participate in the Green Energy Fund competition, which resulted agreement signed, to lease a land plot for the construction of a hydroelectric power plant.
"The implementation of the project will allow to increase the country's generation capacity and increase the reliability of electricity supply in the southern regions," the report says.