Bishkek, Oct. 29, 2026. /Kabar/. Plans are in place to complete 22% of the total construction work on the China–Kyrgyzstan–Uzbekistan railway by the end of the year. Furthermore, the aim is to achieve 110% of the targets set for 2026. Ulan Kulov, Deputy General Director of the "China–Kyrgyzstan–Uzbekistan" Railway Company told during the live broadcast on Birinchi Radio.
According to him, the construction of the railway is proceeding according to the approved schedule. In August, excavation work was completed on the "Kosh-Dobo-2" tunnel, which spans 209 meters in length. "This is one of the shortest among these tunnels. The project envisages the construction of 29 tunnels with a total length of 104 kilometers. The excavation of the 'Kosh-Dobo-2' tunnel is one of our first significant achievements. Meanwhile, the remaining work is proceeding according to plan," said Ulan Kulov.